Re: Misaligned Start Dates for Production Order

$
0
0

Hi all,

 

Any pointers on this issue please.

 

We understand ETO plants use the scheduling type = 3- capacity only that will lock the schedule dates.  It appears that the ETO schedulers are using their established procedure to set the schedule dates for the entire collective orders as 3-capacity only …. At some point the scheduling type changes to ‘2-backwards’ scheduling.  SAP is correctly changing the schedule date based upon 2-backwards scheduling. 


So, we believe the problem is to determine why/how the scheduling type is getting changed from ‘3-capacity only’ to ‘2-backwards’.


Any pointer why it could happen....


Regards

Tushar