Hello R.Brahmankar,
The consistency check has not problem and we had created new versions for other materials and the result is the same in the plant "1300":
Watch the next, I we select "Basic dates" for the field "Prod./basic dates", By default we use the value "Production dates" in that field, in the view or tab Scheduling and execute:
The field are enable to edit, but we need it with "Production dates".
Thanks a lot.